I-215 HOV Bi County Gap Closure Project

Description: In Riverside and San Bernardino Counties, from 91/60/215 interchange to south of 215/Orange Show Road interchange. Construct one HOV lane in each direction.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino, Riverside
City Grand Terrace
Zip Code
 
Senate District
32, 36
Assembly District 63
Congressional District 43, 44
 
Caltrans District
08
 
 
County/State Route San Bernardino 215
Postmile Begin/End 0 5.7
 
County/State Route Riverside 215
Postmile Begin/End 43.2 45.3
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      3031  
Lane Miles Added (HOV)  8.0    15  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Khalil Saba (808)884-8276   Khalil_Saba@dot.ca.gov
Design (PS&E) Phase
Caltrans Khalil Saba (808)884-8276   Khalil_Saba@dot.ca.gov
Right of Way Phase
Caltrans Khalil Saba (808)884-8276   Khalil_Saba@dot.ca.gov
Construction Phase
Caltrans Khalil Saba (808)884-8276   Khalil_Saba@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $61,520 $61,520
IIP Augmentation
$0 $0 $0
CMIA
$18,548 $-191 $18,357
Non-bond Funding
State/Federal*
$90,590 $-63,245 $27,345
Local**
$90,897 $6,942 $97,839
 
Total**** $200,035 $5,026 $205,061

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$6,666 $0 $6,666 $4,624
Design(PS&E)
$14,696 $0 $14,696 $9,887
Right of Way
$10,698 $0 $10,698 $165
Construction
$167,975 $5,026 $173,001 $161,656
 
Total* $200,035 $5,026 $205,061 $176,332

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/01/2009 

03/22/2011 
 

 
02/01/2009 

03/22/2011 
02/01/2009 

03/22/2011 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/01/2010 

03/30/2012 
 

 
08/01/2010 

03/30/2012 
08/01/2010 

06/20/2012 


-3 
Begin Right of Way Phase

End Right of Way Phase
04/01/2011 

03/30/2012 
 

 
04/01/2011 

03/30/2012 
05/01/2011 

06/08/2012 
-1 

-2 
Begin Construction Phase

End Construction Phase
08/31/2012 

08/29/2014 
 

 
08/31/2012 

08/29/2014 
12/03/2012 

08/25/2015 
-3 

-12 
Begin Closeout Phase

End Closeout Phase
09/01/2014 

09/01/2016 
 

 
09/01/2014 

09/01/2016 
12/02/2019 

06/30/2021 
-64 

-59 
Corridor System Management Plan
Adoption Date 06/01/2008       
Implementation Date 09/01/2008       
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 3031
Lane Miles Added (HOV) 8.0 15

Bond Funding Cost
Adopted:
$18,548,000
Current Approved:
$18,357,000
Actual Expenditures:
$17,741,450

 

Status as of December 31, 2023.